Which two things should the Scrum Team do during the first Sprint?

scrum master certification answers

Q. Which two things should the Scrum Team do during the first Sprint?

  • Develop and deliver at least one piece of functionality
  • Develop a plan for the rest of the release
  • Deliver an Increment of useful and valuable products.
  • Determine the complete architecture and infrastructure for the product.
  • Create the complete Product Backlog to be developed in subsequent Sprints.

The Correct Answer is:

  • Develop and deliver at least one piece of functionality
  • Deliver an Increment of useful and valuable products.

Get the full set of questions and answers here: Scrum Master Certification Exam Answers