Which statement is true about the PI Planning event?

SAFe for teams 5.1 certification question-and answers

Q. Which statement is true about the PI Planning event?

  • It involves only the team members who are most qualified to estimate the work
  • It involves Program Portfolio Management to prioritize the Stories presented by teams during the final plan review
  • It involves Product Management and Product Owners on the first day and the rest of the teams on the second day
  • It involves everyone in the Program over a two-day period

The Correct Answer is: It involves everyone in the Program over a two-day period