Which function is responsible for ensuring that the Agile Release Train has the content needed to successfully engage in Program Increment Planning?

safe popm exam questions and answers

Q. Which function is responsible for ensuring that the Agile Release Train has the content needed to successfully engage in Program Increment Planning?

  • Release Train Engineer
  • Product Owner
  • Lean-Agile Center of Excellence
  • Product Management

The Correct Answer is:

  • Product Management

Get the full set of questions and answers here: SAFe POPM Certification Answers


Related Searches: PO PM Certification Answers, SAFe POPM Certification Answers, SAFe POPM Certification questions, PO PM Certification exam, PO PM Certification exam answers, PO PM Certification quiz answers, PO Certification Test Answers, Product Owner Interview Questions ,Product Manager Interview Questions, PO Assessment Exam Answers, Free PO PM Certification