Q. What is one way to establish a team’s velocity?

  • Calculate the percentage planned versus actual Stories completed during an Iteration
  • Add the Story points for all the stories planned for the Iteration
  • Look at The average Story points completed from The last Iterations
  • Add the Story points for all Features completed in the Iteration

The Correct Answer is:

  • Look at The average Story points completed from The last Iterations

Get the full set of questions and answers here: SAFe POPM Certification Answers


Related Searches: PO PM Certification Answers, SAFe POPM Certification Answers, SAFe POPM Certification questions, PO PM Certification exam, PO PM Certification exam answers, PO PM Certification quiz answers, PO Certification Test Answers, Product Owner Interview Questions ,Product Manager Interview Questions, PO Assessment Exam Answers, Free PO PM Certification