Q. What is an anti-pattern for the IP iteration?
- to plan work for the IP iteration during PI planning
- to allow for sufficient capacity in the program roadmap
- to wait for the IP iteration to fix defects
- to ensure all stories and teams’ PI plans are completed prior to the IP iteration
- to minimize lost capacity when people are on vacation or holidays
The Correct Answer is:
to plan work for the IP iteration during PI planning,
to wait for the IP iteration to fix defects