Q. SAFe recommends separating deployment from release. What can help with this practice?

  • Manually test Features and nonfunctional requirements
  • Deploying to staging every 4 to 8 weeks
  • A staging environment that emulates testing
  • Hide all new functionality under Feature toggles

The Correct Answer is:

  • Hide all new functionality under Feature toggles

Get the full set of questions and answers here: SAFe POPM Certification Answers


Related Searches: PO PM Certification Answers, POPM Certification questions, PO PM Certification exam, PO PM Certification exam answers, PO PM Certification quiz answers, PO Certification Test Answers, Product Owner Interview Questions ,Product Manager Interview Questions, PO Assessment Exam Answers, Free PO PM Certification