Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?

SAFe for teams 5.1 certification question-and answers

Q. Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?

  • Agree to add a person from the System Team to complete the work
  • Support splitting a Story into a coding story and a testing story, and then moving the testing story into the next Iteration
  • Support pulling a Story that has not been started
  • Support adding an Innovation and Planning Iteration directly after the current Iteration

The Correct Answer is: Support pulling a Story that has not been started